The rule, as the pack states it

Louisiana sets these when a lot or unit is sold, rather than in answer to a records request:

  • ten calendar daysunder the Louisiana Condominium Act

    Louisiana gives an association ten calendar days to furnish it on a sale for the certificate a selling unit owner needs from the association, from the day the request arrives (R.S. 9:1124.107(B)-(C)).

    “THE ASSOCIATION, WITHIN TEN DAYS AFTER A REQUEST BY A UNIT OWNER, SHALL FURNISH A CERTIFICATE containing the information necessary to enable a unit owner to comply with this Section.” It answers a SALE, not a records request: the selling owner furnishes the purchaser the declaration, the documents creating the association, the bylaws and an eight-item certificate. Two consequences: “The unit owner providing a certificate … IS NOT LIABLE TO THE PURCHASER FOR ANY ERRONEOUS INFORMATION PROVIDED BY THE ASSOCIATION and included in the certificate”; and “A unit owner is not liable to a purchaser for the failure or delay of the association …; however, THE CONTRACT TO PURCHASE IS VOIDABLE BY THE PURCHASER UNTIL A CERTIFICATE HAS BEEN PROVIDED AND FOR FIVE DAYS THEREAFTER or until conveyance, whichever first occurs.” Unamended since Acts 1979, No. 682. “Ten days” is unqualified, so calendar days.

    R.S. 9:1124.107(B)-(C) · Checked Sep 2026

  • ten calendar daysunder the Louisiana Planned Community Act

    Louisiana gives an association ten calendar days to furnish it on a sale for the public-offering information a purchaser needs where an owner is selling, from the day the request arrives (R.S. 9:1141.43(E)(3)).

    “When a lot is subject to a contract to sell and is owned by a person other than the declarant, THE ASSOCIATION SHALL BE REQUIRED TO PROVIDE TO THE PURCHASER ALL INFORMATION REQUIRED IN THIS SECTION WITHIN TEN DAYS OF A REQUEST for the information.” What that information is runs to nineteen disclosure items plus § 1141.43(B)’s “current balance sheet and a projected budget”, “A statement of the amount included as a reserve for repairs and replacements”, any other reserves, and the projected common expense assessment by category and per lot. Note the asymmetry with the rest of the section: a public offering statement is NOT required where the community “contains fewer than seventy-five lots based on the total number of anticipated lots after all development rights … have been exercised” (§ 9:1141.43(E)(2)) — but (E)(3)’s ten-day duty on a RESALE is not limited that way, so it reaches a small community too. New with Acts 2024, No. 158, effective 1 January 2025.

    R.S. 9:1141.43(E)(3) · Checked Sep 2026

Louisiana also sets these on their own clock, not in answer to a request:

  • thirty calendar daysunder the Louisiana Planned Community Actassociations of 26 units or more

    Louisiana gives an association thirty calendar days to make them available for the budget summary, with the basis on which any reserves are calculated and funded, from the board’s adoption of a proposed budget (R.S. 9:1141.34(A)(1)).

    “NOT LATER THAN THIRTY DAYS AFTER ADOPTION OF A PROPOSED BUDGET, the board of directors shall provide to all lot owners A SUMMARY OF THE BUDGET, INCLUDING ANY RESERVES, AND A STATEMENT OF THE BASIS ON WHICH ANY RESERVES ARE CALCULATED AND FUNDED.” Owed whether or not anyone asks. ONLY ABOVE TWENTY-FIVE LOTS: the subsection opens “For planned communities consisting of more than twenty-five lots”, so this rule carries min_units = 26 and a smaller planned community is shown nothing rather than a date it does not owe (0092). What follows is a ratification step rather than a records duty: “Simultaneously, the board shall set a date, which shall be no fewer than ten days nor more than sixty days after the summary is provided, for a meeting of the association to consider ratification … A majority vote … is required to ratify the budget. If a proposed budget is not ratified, the budget last ratified … continues.” That ten-to-sixty-day window is when a MEETING must fall, which no rule kind in this product fits.

    R.S. 9:1141.34(A)(1) · Checked Sep 2026

How a request is answered on the record

Every records request gets a dated receipt the owner can keep.

The deadline for answering comes from your state’s pack and is set by the database the moment a request is filed. No one types it in.

  • The owner names the record in plain language and sends the request from their own sign-in.
  • The request is written first and its receipt second; the receipt carries the date, the time with its zone, and a reference.
  • The board sees the request with the date it arrived and the date the Louisiana pack expects an answer by.
  • The board answers in writing. That stops the clock, stays on the record, and issues the owner a second receipt.

The whole Louisiana checklist

This page answers one question. The checklist is every kind of record Louisiana expects an association to keep — 12 of them — with the retention period, the disclosure rule and the citation for each, and a form that emails you a copy.

Do it now, without an account

These run in your browser on the same Louisiana pack this page is written from. Nothing you type reaches us.

Not on the board? Send this to yours.